Washington Ave Update 6/29/15

Last week the project hit a big milestone with the opening of Section A (Downtown) on Thursday morning.  This was two weeks ahead of the contractor’s deadline!  While there are still some clean-up items to address, the work in this section is substantially complete.  Additional progress was also made in Continue Reading

Washington Ave Update 6/22

Things are still progressing well and most of the activities are ahead of schedule.  Section A work (downtown) is wrapping up and should be complete later this week.  In Section B the underground work is nearly complete and street construction will begin later this week.  The following is a progress Continue Reading

Washington Ave Update 6/15

Today marks the 10th week of construction since we started the project in late April. There has been a lot of work completed in the last ten weeks…but I am sure many of you are ready for it to be over. Section A (downtown) is nearing substantial completion. At this Continue Reading

Washington Ave Update 6/8

We had a good amount of progress last week in both sections of the project.  We saw the first of some new pavement in Section A and more underground utilities go in on Section B.  The upcoming week will be have a significant amount of visible change and progress in Continue Reading

Washington Ave Update 6/1

We are heading into the 8th week of construction and there will be a fair amount of activity this week (if the weather cooperates).  The downtown area will see the first of some new street pavement and Section B (Willow to Frazee) will continue with underground utility construction.  The following Continue Reading